Žabljak
Umjereno oblačno
22.1 °C
Pljevlja
Umjereno oblačno
25.3 °C
Herceg Novi
Vedro
28.9 °C
Nikšić
Pretežno vedro
29.0 °C
Cetinje
Pretežno vedro
30.4 °C
Bar
Vedro
28.1 °C
Podgorica
Vedro
34.8 °C
Ulcinj
Vedro
28.8 °C
Kolašin
Pretežno vedro
25.7 °C

We use cookies and google analytics tool to optimize the delivery of digital advertising to you. If you decline personalization of ads you will still see digital advertisements, but they will not be as relevant to you. We never collect sensitive information, and do not sell any of the data we collect. Under the GDPR regulations browser cookies are now considered sudo-anonymized personal data and since we use cookies to deliver relevant advertisements to you we would like to get your permission to do so.

I don't want my data to be used anymore for analytic purposes.

Montenegro

NURKOVIC AT THE CONSTRUCTION SITE 11. 07. 2019.   >>  19:16 0

NURKOVIC AT THE CONSTRUCTION SITE

The first Moracica section connected

Merging of one segment of the spanning construction of the Moracica bridge on the Bar - Boljare highway has been completed. The entire bridge is expected to be connected by September this year, the Ministry of Maritime Affairs and Transport announced. New deadline for the completion of works is expected to be met in due time.

Minister of Transport and Maritime Affairs, Osman Nurkovic, with his associates and the CRBC representatives, went to see the entire section of Bar-Boljare highway.

Satisfied with the volume of works done on bridges, tunnels and open roads, Nurkovic once again expressed the expectation that the new deadline for the completion of works, September 2020, will be met.
“Understanding of all involved and assistance to the contractor is required in order to get this very complex project finished. It’s not only construction of Moracica bridge that is complex and demanding, but also the Verusa loop, with viaducts and access roads and bridges”, said Nurkovic.

As the Ministry announced that, so far, around 96% of works on the construction of bridges, pillars and foundations has been completed, and 54% of works on spanning constructions.

“Spanning construction of three bridges has been completed: Gornje Mrke, Suvovara and Preslo, whereas five bridges: Mistica, Uvac 1, Uvac 3, Pajkov Vir and Jabuka have been finished in one highway lane only.” says the statement.
Around 80% of works on the spanning construction of Moracica has been completed.

Komentari 0

ostavi komentar

Ostavi komentar

Pravila komentarisanja sadržaja Portala RTCG
Poštujući načelo demokratičnosti, kao i pravo građana da slobodno i kritički iznose mišljenje o pojavama, procesima, događajima i ličnostima, u cilju razvijanja kulture javnog dijaloga, na Portalu nijesu dozvoljeni komentari koji vrijeđaju dostojanstvo ličnosti ili sadrže prijetnje, govor mržnje, neprovjerene optužbe, kao i rasističke poruke. Nijesu dozvoljeni ni komentari kojima se narušava nacionalna, vjerska i rodna ravnopravnost ili podstiče mržnja prema LGBT populaciji. Neće biti objavljeni ni komentari pisani velikim slovima i obimni "copy/paste" sadrzaji knjiga i publikacija.Zadržavamo pravo kraćenja komentara.

Da biste komentarisali vijesti pod vašim imenom

Ulogujte se

Novo